7-2 What are the inspection contents before the first start of the screw air compressor?
فئات

7-2 What are the inspection contents before the first start of the screw air compressor?

Before the first start of a screw air compressor, inspect for debris, electrical safety, oil/gas levels, water lines, equipment anchors, pipeline connections, safety devices, and control panel functionality.
تفاصيل القضية

Answer: (1) Remove wooden wedges, pads, clamps and supports and other debris on site.

(2) There should be no debris, flammable, explosive and corrosive chemicals inside and outside the machine body.

(3) Check the setting value of the motor overload relay and whether the electrical wiring meets the requirements of the safety regulations. The insulation must be grounded to prevent short circuits. The power switch should be located near the unit.

(4) Fill the oil and gas barrel to the upper line of the oil level gauge.

(5) Connect the water line, close the drain valve, and check the opening status of the air outlet door. The anchor screws of all mechanical and electrical equipment are complete and firm, the protective covers are complete, and the connectors and fasteners are installed normally.

(6) Check that the oil and gas pipelines are connected correctly and the position and status of each valve are correct.

(7) The oil pressure, temperature, pressure difference, solenoid valve, overcurrent, undervoltage and other safety interlocking devices should be calibrated and debugged according to the provisions of the equipment technical documents.

(8) The local control panel and installed equipment are in good working order and the indicator light test is qualified.